Procurement -II, III Lecture Summary
00:00:18
Sir, there’s more to it, like a lot more. Then after that, a lot in favor of the third person. Okay? Exactly right. Nailed it. Exactly nailed it. And if it were me, I’d base it on the value of money. Alright, I’ll start again, and Inshallah, I’ll continue this during the break. Okay? Okay. Wait a minute on the slide, don’t go back. Should I go back? Okay, go back. Cut it there. Stop, stop, no, no, no, just leave it. Leave it, you leave it. Let’s start. Yes, sir. Okay, on this slide, we had finished before the tea break. So now I want to start again from here.
00:04:49
Alright, as I said right from the start, whether you're supervising procurement or you're a member of the procurement committee, you need to know where your role begins and where it ends. This slide helps us understand exactly that—whose role ends where, and whose role starts where. So, we need to look at these things. Before any procurement, there's a need assessment—basically, the need has to be generated first. This need can come from social factors or due to changes in technology. It can also come as a demand from the end user.
00:05:42
It can happen. All these factors create a need. In my opinion, what’s the biggest need? I want a motorway built quickly from Kohar Tunnel to DI Khan. That’s the need over there. Because every year, hundreds of people die. That’s a real need. It’s important. Absolutely. We all agree on that. Just like typewriters automatically became obsolete, the need automatically arose. For example, recently, an advertisement came out for civil judge positions. Some have been recruited and have just gone for training for six to eight months.
00:06:21
After a month, they will be sent to their respective courts. So, building courts for them is necessary. The internal systems, the computer setup, the rooms you have—all those things need to be developed for them. This need has to be justified, whatever you take. There's just one example that will make things clearer after all these talks. I'm speaking practically—between Ayub Medical Complex in Abbottabad and the Peshawar Hyderabad F5 area, up to Peshawar Institute of Cardiology, there's a huge attached area, near by.
00:06:58
Lower Dir is one of those areas where, even though it’s a public sector government facility, there isn’t a single angiography machine that can place stents for heart patients. Does that mean no one here has heart attacks? Of course, they do. So if there’s a need, why isn’t there one in the public sector? The MHO working in our district board in Mardan thought the same—that there should be one. Once they decided it should happen, they approved it during a board meeting. Now, what do you think is the next step? What should happen next? Arranging the funds, and meanwhile, during the approval process, something else...
00:07:35
It's something, and a pretty awesome thing at that. But if you think about it a little and explain, it'll be way more fun. You're about 80% there between these two. The need has been generated and approved. The boss said we need to allocate funds. In between all this, there's one more thing. Quantity—let's say just one machine is needed. Market assessment. Market assessment is like the second part of the need—how much does it cost? Only then will they consider your point, like when you've already arranged the funds. I've been to Rawalpindi Institute of Cardiology and around there; that machine costs roughly 51 crore. And the machine...
00:08:19
It's not like you just stand there and perform a stunt like an injection, and then boom, you go home. You have to stay there for three or four days. You need to design a whole ward for beds, with ventilators and everything else, creating a proper environment inside. The whole thing was going to cost around ₹51 crore. The assessment is done now, and after that, we went to get the funds approved. We approached the Health Department, then the Finance Department, but the funds haven’t been released yet. The allocation has been made, yes, but the money hasn't come through. Once the allocation is done, then our work starts.
00:08:51
Let me also tell you that I've spent about 8 years and 4 months—actually 8 years, 4 months, and 3 months—in Mardan. I was a member and secretary of every procurement committee there. Got it? The secretary was like the goalkeeper; I was the wicketkeeper. Because I had to handle all the coordination and planning of the entire process. After that, I added ₹51 crores—₹10 million—to the standard procurement plan format, which you will also practice, God willing. And I specified that this amount was for civil works.
00:09:24
I coordinated with the works team and prepared the tender for the machines myself. I estimated that the building process would take me about three months, and the machines would arrive in about three to four months, so around six to seven months total. At the same time, Nespak was our consultant. We completed the tendering process with the understanding that if the building work took a month or a month and a half, the building would be ready in about four to five months. This was our parallel procurement plan. There were a lot of other things too, but I’m specifically talking about this project. Is that clear so far?
00:09:52
We included it in the planning. Now, as you know and I know, any involvement over ₹1 lakh requires committee approval. Why? Because for anything over ₹1 lakh, even between ₹1 lakh and ₹5 lakh, there has to be a comparison, right? There should be at least three bidders. So, wherever there’s a comparison, committee approval is mandatory. Why comparison? The committee reviews the comparisons and recommends who should win. Now, the committee deal is for ₹51 crore. Yeah, brother, get the committee involved. I'll explain later which committee it is. For now, let’s move ahead.
00:10:27
Let me clear this up right here. There was a goods committee, which had the most senior professor, a surgeon from Cardak. They had doctors from Cardak. I was handling finance. We put everything together. What was this committee’s job? To develop the bid solicitation document. The standard was already there. We took it from there, added our requirements, made our own criteria, created our NIT, and prepared the tender notice. That’s how it got done. Now, something like enlistment or pre-qualification—this is optional by law. Whether it’s for goods, works, or services, it’s optional. It depends on the context. Wherever there’s a shell, there it is.
00:11:07
You know better about the mandatory stuff. That’s where I took advantage. We directly developed the bid documents for the single-stage two-envelope process. We had the bid solicitation documents ready and even sent them directly to newspapers and cameras. Back then, there was no e-procurement. From here, we developed the committee, but then dropped it because you left. Meanwhile, it got published in the newspaper. Bidders took the bid documents from us. After 15 days, or the fixed time period, we opened the bids, examined them, and did the evaluation. Once the evaluation was done, then directly...
00:11:43
The contract isn’t given to any bidder right away. The results are announced under Rule 45; it’s all set in the shell. There’s a 10-day period called the "capra," and it’s mandatory to have this on my website. On the 11th day, go ahead and award the contract, okay? So here, we’ve allowed those 10 days. I’m following the routine. I’m not touching the June issue right now. On the 11th day, after announcing, if there are any grievances, I address them first. The grievances were from sir, from Asgar Sahib—he’s a supplier from Siemens, an authorized dealer in Pakistan.
00:12:22
Their grievance was about why they were given certain scores when they clearly had no relevant experience anywhere. I was bound to resolve their issue within 5 days. Whether I addressed or closed their grievance, the department was responsible to communicate with them within those 5 plus the next 3 days. If the department didn’t do that, on the 9th day they would go directly to CAPRA, and then CAPRA would resolve their issue within 51 days. Yeah, they could still go there even if I had already communicated my decision to them, but...
00:12:58
This isn’t satisfying. Bro, I’m not satisfied. I’m telling the department straight up: go directly to the camera. Clear? Now, after that, if everything is going through the routine ideal procurement process and the grievances have been addressed, then we have to award the contract to the successful builder. This is the whole procurement lifecycle. Now whether you’re a member, or the chairman, or the head, or the approving authority—it’s on you to see where your role fits in if you’re not on the committee, and if you are on the committee, then the entire role is yours.
00:13:34
Okay, so if you’re the head of the committee—sorry, you’re a session judge—what exactly is your role in all this? Where do you fit in? Your direct role comes in at three different points throughout this whole process. Number one, you have to give administrative approval. And if there are different cases that come in, that administrative approval comes from somewhere else, right? You’ve already given approval from the High Court. Now ideally, if someone wants to procure something for their office, your role kicks in before the annual procurement plan. You give the approval there. One, then...
00:14:09
You’ll also need to give the financial approval at this stage. Got these two points clear? The third thing, which is the most important and a legal requirement, I’ll explain in detail tomorrow. You’ll also be the chairman of the Grievance Redressal Committee. If you’re not available, there will be a committee under you that you’ll lead. If you don’t want to handle it alone, you’ve been given the role of GRO—Grievance Redressal Officer session judge. Just find two officers, a judicial officer, GRO, and advisory GRC members—eight members total, maybe three, five, seven, or nine. These roles will cover three different places if you are the head.
00:14:54
So, your role is set. If any of you are juniors, members, or the chairman of the procurement committee, then your role is part of this entire cycle. Is that clear? Now we've come to the guessing stage. Any questions? The advertisement is under the 'haan haan' rule for one place. I'll keep that question aside for now and explain it after the procurement plan. Okay? Someone will have fun answering that over there. Should I go back? Okay, I'll go back. So, every procurement committee has a member who's the technical expert.
00:15:53
Members say, right? If that guy doesn’t have the capacity and something like this really happened with me. In this angiography, our biomedical engineer didn’t understand much, so the rule is that you can take another technical expert from your line department. We took the line department people from LRH. We got one from PIC. For IT, you took the IT guys. Exactly like that. Only for Wahid civil works, you can even take a procurement committee member from outside on payment. For the rest—goods, consulting services, and non-consulting services—you can...
00:16:32
You can request from within the department, or from another expert in the same district, like someone from the IT department, a college, male or female, any IT teacher, anyone. Or you can also request from your head office or the High Court. This falls under CAW in law, which comes under civil works. According to Rule number 32(2) in law, you can make this demand. This provision is given to you for civil works. You can also hire from the market outside. Moving forward, shouldn’t both be involved? The competent authority.
00:17:30
I’ll teach the definition first. That comes next. And I only teach this part here. I’m just bringing this slide here for this section. Yes. And this is wrong. And this is wrong too. You all have pretty much wrapped up the procurement committee now. Yes, yes, I know this is mostly done now. I’ve been working closely with you all for the past two or three years, right? Before that, it was a lot more. I’m bringing this upcoming slide especially for you all so we can clear things up right here. Got it? Should I move on from here or stay here?
00:18:15
How many phases of procurement are there? If you don’t know, just guess. How many phases does procurement have? Just take a wild guess like a college student, please! Guess how many phases there are and tell me—even if you’re wrong. So, what are the five phases? Somebody else tell me which ones they are, or if you have any in your mind, say one of the main components or one of the main phases. Someone else, you’re very good, another person, very good—tell some subcomponents too. Come on, just throw some guesses. Evaluation is also a subcomponent. Constitution of committee is also a subcomponent of that phase.
00:19:12
One of the biggest challenges in public procurement is that there are basically three common failures you'll notice everywhere. Planning fails, tendering fails, and post-evaluation or contract administration fails. Nobody knows that a Chitral advertisement will pop up on the server until just before it appears on the newspaper or the EPD website. All the work behind the scenes is faulty, and the stronger this failure is, the better your opportunity to step in. Now, whatever points you've raised fit right into this framework.
00:19:59
They're falling inside or somewhere within this. Now let's see what's inside. So, right now, watch what we do in planning and faith. Like Saeed sir was just saying, cost assessment and those things come in. Need assessment and justification—bro, 10 judges are coming, either after 6 months or 4 months. Bro, we need a motorway, angiography needs to be done; there’s both justification and need. Then I said, initial market survey—bro, so we know the cost. After that, budget allocation; once the funds are allocated, then in the procurement planning form, you put that amount in.
00:20:45
Got it into the planning stage now. It's been added to the planning. The session judge will think here whether this is a one-man show or if our procurement committee is needed in this process. So obviously, involvement is necessary—it's mandatory. Then our committee will be formed again, which usually happens once a year. Try not to name the committee by specific people since you guys change frequently by designation. Yes, now the committee needs to handle things like pre-qualification, and for that, we'll move to advisory preparation of direct bids and...
00:21:20
The Administrative Approval Board gave the go-ahead for the citation document advertisement terms. The double A specification has been finalized today because the advertisement needs to go in the newspaper tomorrow. The funds are either released or in the pipeline. You need to make sure of three things before issuing any advertisement. Then you'll be able to move on to the next phase. So, what do we have in the next phase? If I look back, it says the tendering phase. Let’s check what’s included in the tendering phase. The ad has already appeared in the newspaper, and it’s uploaded on the ePad. KP.
00:22:09
I went to the Pepra website. Uploaded it on the department's website. Distributed it to the builders. All this is solicitation. Put it up outside your court's board. Just sit and distribute the advertisement on social media, keep disseminating it, and bids come in response. There's another thing that happens in between, but once you get more free time with me, God willing, I’ll give you knowledge one or one and a half times more. Then I’ll talk to you about it in great detail. But for now, this needs to be done.
00:22:47
The newspaper was published, and after 15 days the bids were received. Once the bids are received, they need to be opened, examined, and evaluated. According to Rule 45, after evaluation, the result has to be announced. Rule 45 also says the result should be posted on my website for 10 days for authority clearance. If that's cleared, grievances should be addressed, contract negotiations done, and the contract awarded to the successful bidder. Sir, the contract was awarded to Khalid Sahib. Then, after 28 days, the second, third, and fourth bidders should have their bid securities returned. Why? Why 28 days?
00:23:28
Talking about the day? It’s mentioned in the standard bidding document that this shouldn’t happen. Right now, I’m giving them the letter of award so they don’t run away. I don’t do contracts like that. So, I’ll keep 2% as security for the fees. I already have the second one with me. Let them come, let them come. They ran away. 2% as security for the fees. If they’re responsive, complete everything, then they come to the third stage. And so on, but it usually doesn’t go beyond that. At most, after the second or third day, for the security for the fees, they want to re-advertise and impose penalties. Some other department wants to do that. Then that...
00:24:05
Decisions are made based on the situation. Sir Khalid won. Everyone else has to return the CDRs. Now, whether it's me or them leaving doesn't matter. I'm just the supplier from the department. I awarded them the contract. They've gone to Japan to arrange the shipment. This guy gave me a contract with 10% security, which sir has deposited. We sat down and negotiated every clause of the contract, and after that, they left. After about three or four months, they brought the stuff and installed it at my respective place, which was already prepared.
00:24:43
After that, the inspection was done. The quality control, according to the timelines and specs, everything is absolutely fine. On the day they deliver, they’ll also submit the invoice. Then the invoice goes into their process, and after that, they get the payment. Is that clear? These are the three phases in procurement: the planning phase, the tendering phase, and the contract award committee. Once this starts and the contract is awarded, it means they’ve successfully provided good quality stuff as per the specifications.
00:25:33
The failed one is requesting the exact same specification that I originally named. Like I have the specification and the third party involved can raise an objection saying, “You already awarded it, but you didn’t give the thing to anyone for handing over.” I could have given it to you too. This very question has been asked to me 8 to 10 times right here in this room, during training sessions for senior civil judges. Here, three or four people grilled me hard, telling me to resolve this issue. You can’t change the brand name, got to stick to the brand.
00:26:25
The recording is happening too. I'm saying this in front of them. You don’t need to change the brand. If a newer model comes, you can take that. I can show you in your law. And I even sent them screenshots to the judge. Tell me the name too. You were there as well, remember? Sir, that’s exactly what I said. I didn’t talk about any changes. You were one, and recently there’s another gentleman at the High Court. He’s Khurshid’s brother—I’ve forgotten his name right now but I have his number saved. He recently made a big deal out of this. So, I sent him the screenshots.
00:26:55
We’re definitely not changing the brand. Take the upper model instead of HP. The upper model hasn’t done anything wrong. Although Kera is saying something wrong. Kera had advised Sir Khursheed’s brother not to do it. Then I showed it to the legal team. I said Kera’s people haven’t even done procurement worth a lakh till now. They only sit on rules and regulations. I told him, anyone who’s actually playing in the market knows this. Then I took it out legally and sent it to Khursheed Sahib’s brother. He said, dude, this is completely fine. Then they showed it to the High Court judge.
00:27:25
He said, "That's totally fine, just keep it like that. Don’t change the brand." Why? Because if you got an HP award instead of HP—or rather, if you switch brands—then the Dell guy will see that and think, “Hey, I had this same thing too, so why didn’t I get it?” So, take the higher-end HP model. Otherwise, if you change or re-advertise, sir, you haven’t changed your sentence, just move forward. This is actually in the law, in the standard bidding documents, it’s written somewhere that this reason—non-provision of this particular good—is not acceptable. No worries, it just gets discontinued. In manufacturing, the higher model is what comes in.
00:28:02
Hey, just give us the upper model, what's the difference? Same terms and conditions, same price, same warranties and guarantees. Yes, without changing anything. Sir, if the specifications are the same, all three specs are the same, then what’s better? What you said, sir, is a really deep point — you’re saying all three have the same rate. But when I show you the highest-ranking fair bit, they might score around 72, 78 in technical marks, like 80 even. When you put that price into the formula, this question still remains unpaid. I’ll prove it tomorrow when I do the practical. So at that time, definitely whoever...
00:28:55
The price gets adjusted within that formula. In my life, it's never happened that the prices are the same and the technical numbers are also the same. So if you plug them into the formula, automatically someone with the highest rank ends up at the top. I’ve made that clear. Don’t get it? I admit it. I’ll explain it to you. And the effort has stopped—we’re not just doing this randomly, but sir’s question is something else, it shouldn’t even happen with the brand. That’s exactly what I was gonna say, sir, or practically speaking—like I said before—this question is kind of on you when it comes to prices.
00:29:48
It's not possible for the same technical members to have exactly the same technical scores. It hardly ever happens. In all my 9, 10, or 12 years of practical experience, I've never seen it. They have a formula for that price inside their technical marks, which is quite simple. I've taught it to you before. If you put it into that, even a tiny difference of 0.0001% in the ranking will make sure the top candidate gets the contract. That's the reality. But we'll explain this better tomorrow.
00:30:25
No, that’s exactly the model, that’s the formula. This is the formula I’m going to teach you. This is what I want to show you – how to get your ranking up. That’s my responsibility, not yours. Most of the time, whether it’s anesthesia or those big machines like hot lungs, ultrasound, or photocopy machines, I’ve always bought them at the highest price. There’s no need to go for the cheapest option. Capra said this back in 2012. And there’s a formula for it, which I’ll teach you tomorrow, God willing. Now we’re getting into the formula. After that, it’s my responsibility. Even the whole audit team knows this. Everyone does.
00:31:14
You know we check the rankings. I’ll explain it to you tomorrow—it’s a perfect example of a generator. God willing, we’ll get a generator with some support from you all. Yes, your question? About what? The lowest bid concept is pretty much done now. Just hang tight. If not today, then by tomorrow morning, God willing, your issues will be resolved. That system is over now. We’ve moved on a bit further. If you want, definitely ask the procurement committee any questions related to the committee. I’ve covered this whole legal framework—
00:31:52
An hour ago, the website showed you a slide about the legal framework. These documents, from the acts that the captain made till the latest notifications. When I went through all of them, carefully searching every single word, I found the word "committee" appeared in eight different ways in the entire regulation. This is my own research into the whole procurement framework. I found eight types of committees. Eight. You only know about the procurement committee and the GRC. Let's go.
00:32:25
Let me tell you six more things. There are six more committees involved in this procurement process. Now, you might think you’re not connected to them directly, but somewhere along the line, you are linked or at least should be aware of them. Number one is the Procurement Committee, which you all know about, and it operates above the department level. At the PE level, half of the goods, half of the works, and half of the services fall under it. In the Law department, they’re separate—there’s a committee for goods, another for works, and another for services, each with an odd number of members. The members are odd in number so that it’s easier to make decisions.
00:33:02
Yeah. When action is taken, it should be done halfway. There should be another committee with eight members, and that should also be at the department level. If a building is being demolished, then the CNW or the respective authority will handle that – we’ll talk about it tomorrow. This doesn’t concern you. This CNW is above the level of Public Health Engineering, Irrigation, and Local Government departments, meaning that besides department-level committees, there should be one above them too. There’s no restriction in KP PEPRAs about grades—like, someone from a particular grade can be on the procurement committee, and someone else can’t. This is the way it is.
00:33:42
It says there should be five members. The chairman should be from '19'. The rest from Gilgit-Baltistan, Balochistan, Quetta are putting restrictions for grades 17 and 18. But CAPRA or Federal PEPRA haven’t put any such restrictions anywhere. There’s also another committee that only handles CNW, and that’s above the provincial level. But both of these are just related to civil works, especially civil works. You get what I’m saying? The way you’re saying, Miss Nazia, about how can we go to the lowest pay? We’ve already stopped taking goods at the lowest pay.
00:34:29
We usually get the routine stuff—papers, stationery, pens, anything you have lying around. We don’t take equipment or instrument-related items at the lowest rates right now. Technically, for goods, we go with the highest-ranking fair bid that comes up. But recently, we've started applying the highest ranking to civil works too. However, there are some special conditions: the ranking approval has to come from a committee in the Civil Secretariat's PD department, supervised by the Additional Chief Secretary. If that happens, then even civil works will follow the top-ranking rates.
00:35:01
Normally, when it comes to civil stuff, we go by the lowest bid for civil works, like I taught you in Non-Consulting. But there's one committee that's for exceptional cases only. This provision is set by the department. It's the fifth committee, and you don't have anything to do with those first three. But you do deal with this one. You always get routine things for your office, like paper reams, water, glasses, stationery – whatever you need. These are usually procured for the whole year. For day-to-day things, you handle tenders regularly.
00:35:34
No, it's not like that. We're not crazy to handle these tasks every single day when there’s plenty of other work in your office or mine. What we usually do is set up a tender called a framework contract. It runs from, say, July 1st to June 30th of next year. The law says you have to follow it strictly, and you can extend it for another one or two years, but the maximum is three years. The law also says there has to be a committee—either at the department level or at your head office level—that approves any extension. But honestly, since you’ve got RDS right in front of you, you could probably approve it yourself.
00:36:13
You’re covered under Delegation 2018. But as I mentioned earlier, the committee will extend it for next year—like, “Hey, extend these rates and stuff.” We’ll talk about this in detail later. According to the KEPRA Grievance Redressal Rules 2017, which I’ve mentioned before, if there’s any complaint against them, it can’t be against these two. The Head of your Department in your office will be the GR Officer, the Grievance Redressal Officer, himself.
00:36:52
No, I just want to do it myself. I don’t want to sit and make decisions alone. Bring two more members, make it four, or six, or even eight members, and then develop the GRC (Grievance Redressal Committee). Who’s in which committee? Yes, I know. No, no, no. The budget is allocated in their name, but if you’re a DDO—like, for example, the senior civil judge somewhere else—and the budget is assigned to you, then you cannot be the chairman of the committee. How can you be chairman of the procurement committee? But for grievances, you are on it, right? As per the GFR Rules 2017, since the budget was allocated in your name.
00:37:48
You’ll be giving financial approval, administrative approval, and also handling grievances. You can’t be the chairman of the procurement committee because your role is strictly that of the GRO, either personally or as part of the committee. Regarding the video, sir, there’s no real issue. Yes, there is a staff member officer involved, definitely, but the head will handle it—not managed by the GRO. The procurement committee chair can’t be the guy in the video; that’s not possible, neither for anyone else like a civil judge, senior civil judge, or any officers.
00:38:39
I know they’re few. That’s why I’ve been saying there’s no strict rule about grades. No restrictions on grades. But I’ll clarify a bit more as we go. I’ll take you along step by step, okay? Up to here, clear? Let’s move on. Now, about this committee—understand that this committee, or that committee, or their subcommittee, or this other subcommittee—they can form one combined subcommittee. I gave you an example: my biomedical engineer didn’t have enough authority to evaluate such a big angiography machine’s specs on his own. He got PIC...
00:39:20
And from LRH, our committee has formed another sub-committee. That’s settled. Similarly, if you're disposing of something or holding an auction, form a sub-committee for that. The main committee will be someone else. What’s the role of this market committee? For example, if you say, “We got a server, but we want to check it out first.” So, another committee is formed to have everyone go and see if the same setup is installed in Peshawar. Before awarding the contract, check if the same thing is installed in DI Khan too. The committee is told to go and have a look before awarding.
00:39:50
Contract. So, the authority is with you. You can take it up. If you want to have a presentation, like, “Hey, come on, this is how the nature of procurement is,” then you can ask for it. If you or the committee don’t have time, a sub-committee can be formed that will technically review everything for you. They have the authority to handle it like their own responsibility. But this sub-committee will give the report to the main committee, not to the head, or the session judge sir or ma’am. Their job is just to report to the main committee, which will then make recommendations.
00:40:25
The procurement head of the department, whether financial or administrative, got it—let's move on. Next, there’s no need for these eight types of committees for amounts up to ₹1 lakh. For anything from ₹1 lakh to billions, trillions, yes, committees are required. One more thing—they asked a really good question: is there any limit to the committee, like up to this amount or that? For amounts over ₹1 lakh and ₹101, a committee is mandatory—I’ve already explained that. Now, if your department develops its own regulations, since it’s a big department—I’ve worked in NAB before. The DG of NAB was KP, and his...
00:41:17
By now, the time must have increased even more. Their total delegation was up to ₹5 lakh. Deputy Chairman had a delegation from ₹1 lakh to ₹10 lakh. Chairman's was ₹10 million and above, ₹1 million and above was unlimited. You make your own regulations. CAPRA is silent. But the committee doesn’t function below a lakh. You can form committees above a lakh. You can also form committees below a lakh. But here, you won't find anything. If needed, see all the committees – this main committee, if even one member is not available, then the committee’s chairman, with your approval as a session judge and competent authority, can do ____ (sentence incomplete).
00:42:21
They formed a committee. It may or may not include these members, and it can be completely different altogether. This isn't mentioned anywhere specifically. It's decided based on the nature of the procurement. For example, when we had our technical member, who was our biomedical engineer, we included him in the sub-committee while taking the cath lab’s angiographic engineer as well. Even though he was our technical member on one side, here he was also a member, and two more were added along with him. They then made the report, or they may not include any of these members at all and form an entirely different committee. Clear?
00:42:51
Got it? Yes, sir. Yeah, that’s all written in your own regulations, so it’ll follow accordingly. Just like how I shouldn’t say yes automatically—I’ll explain more ahead. Give the water bottle, please. Now, coming to foreign matters, how does foreign work? Each department handles it separately; this is legal language, rule 32. Suppose there are four people in total, and three are on goods, if needed, you can take them out for service, though you usually don’t need to. If you include them, there’ll be four guys. If the whole office is involved, then it’s another competent authority.
00:43:59
How many members should a committee have? At least three, or preferably three or more. If there are odd numbers of members and at least three, what should their designations be? Who should be in that committee? Very good. Very good. Absolutely right. And the third member should be a goalkeeper, wicketkeeper, or secretary—minimum three people. If you want to have at least five, then rule number 32 also says you should take members from your department: finance, planning, or your own department. If you don’t have a technical member, as I’ve mentioned before, you can take someone from your own line.
00:44:41
Get it from the department. You can get it from your parent department or anyone else. But there’s always a technical member on every committee. That’s why I’ve already said, remember, don’t name the committee members randomly. The technical member should be nominated, keeping in mind the nature of the procurement. If you’re buying IT stuff, call in the IT guy. If you’re buying anything else, like stationery or whatever, nominate the person accordingly. You’ve already given the status yourself. Madam has explained everything, the decision is by majority, but here a veto power has been given to the technical member.
00:45:19
You have to give weight to the member. Like, if the technical guy says, “Hey, this machine is faulty,” but my brother says, “No, this is exactly what we asked for.” But it’s not giving what we want. It’s messing around with us. This member, yeah, having this member in the committee is important. And they have veto power. If they say no, the head of the department can cancel the whole process, even if two other people agree by majority. The decision has to be by majority, but this member still has the veto. Because tomorrow, this same guy is the only member of the procurement committee, even after 8 months.
00:45:54
When something comes in, it’ll match the technical specifications and what’s already there. But it’s not written anywhere that this person will always be the member. The member could be someone else competent too. But most of the time, like 99%, this same person ends up being the inspection committee member. Now, say you need some IT stuff and there’s no IT person in your office at all. Tomorrow, you might call in some IT expert from a college, maybe a guy or girl. But if they get transferred or posted somewhere else, then the new guy who replaces them will come in.
00:46:27
Check it out. Most of the time, this is exactly what happens. But if it doesn’t, then who else would it be? Sometimes, I do have the camera turned off. But remember, from my own life experience, I wasn’t directly involved in decision-making in NAB, but I was involved in interrogation and investigation. Till today, thank God, I’ve never seen a situation where someone—God forbid—ended up somewhere bad. Either the approving body gets caught, or the technical member gets caught. From what I’ve seen in all the NAB cases I’ve reviewed...
00:47:09
The person who's interested and who approved this process—be it financial, technical, or administrative—is usually the same guy. Most of the time, it's the same people. Most of the time. Just don’t let me say any more than this, so I don’t get caught tomorrow, okay? There’s no kind of restriction grade or prison. But I said I’d explain this a bit more. There are three types of people who can’t be part of the procurement committee. We’ve pretty much covered this, but let’s go over it again. Repeat.
00:47:44
Mistakes have been made. There are three types of people in your department who can't be part of your procurement committee. Now tell me, who are they? Very good. First, the person who is supposed to audit the bills can't be on it. He or she is like a nobody to you. Second, the investigator—your internal audit manager—can't be in any committee, whether it's GRO, GRC, or procurement. They're never put on any committee. And third, a Class Four employee can't be on it because they don’t have decision-making or voting power.
00:48:28
Her job was just cleaning and organizing files, bringing your files and taking them back. Yeah, she couldn’t even do that, and that too is unlikely since she’s the head, just like Madam said. Yeah, that’s definitely not possible. But these three types of things can’t happen in the procurement committee. I’ll explain it now. For those I’ve trained before, this won’t be new, but for others it will be. We’ll cover the next slide along with this. So, what does this committee do? It develops the bid solicitation document. I’ve been saying this from the start. This committee is responsible for both technical and financial evaluation. That’s about it.
00:49:11
The bit document. The committee’s job is to prepare and publish the evaluation report. This is the most important thing on which madam replied about making recommendations for awarding the contract to the competent authority. Meaning, the competent authority is someone else, the committee is someone else, the DDO senior civil judge sir is someone else, the committee is separate. Because all this has to go to him for approval. Okay sir. And to constitute the entire committee for evaluation. That’s the point. Got it? And to perform any other function like visiting places or going somewhere else.
00:49:52
So, if anyone wants to sit down for negotiations or whatever, that’s covered in your competent authority definition section. We had a big discussion about this slide last time. And if anyone still feels like discussing it today, go ahead and have your fun. A lot of you already know this stuff. Number one, whatever’s in your financial delegation of power is enforced for the timing that applies nowadays. In other cases, if something comes from the High Court, and there are other financial laws or rules duly approved by the High Court, etc.
00:50:25
Yeah, Supreme Court says, brother, you become the chairman of this. You're the head of procurement here. Like in case B, in that scenario, second scenario, third, you exercise the financial power and approve the contract award for procurement of goods. Or in the third case, if you get some direction from above that you should handle everything, then you become the competent authority. This is clearly stated in Section 8 of the Act, and it’s a really good thing. I like it. So, yeah, how many methods are there for procurement, what are the ways?
00:51:04
Okay, who all said "very good"? You answered absolutely right, about 70% correct. But when it comes to terminology, we need to use the right terms. How many methods are there? Ask that. Very good, very good, two. And both madams explained it like this: one is through advertisement, the second one is through another way, and the third is there as well. There are a total of three methods worldwide—from the USA to Pakistan’s KP PEPA—only these three methods exist. What you said, what sir said, is the second method: restricted bidding, pre-qualification bidding, limited bidding—between certain parties only.
00:52:04
Let me explain pre-qualification among people. I’ll talk about pre-qualification in detail later, but for now, here’s a simple example to help you understand it easily. I have a really clear and neat example. Remember the Bank of Tyber closing with Pak Bakers? The seven-story building, everyone saw it. Pre-qualification was done for this building, and 29 bidders participated. Out of those 29 bidders saying they could do the job, only eight were shortlisted after pre-qualification. These contractors were owners of immense wealth worth billions and trillions. But from here on, downwards...
00:52:44
You can definitely build an amazing irrigation canal up to Kostan. But the structure shouldn't be designed like a bank’s. Because pre-qualification only happens in a specific field, right? I’m doing the pre-qualification. Brother, the reason I’m pre-qualifying you is to see if you can handle my upcoming big project or not. Out of them, eight guys had built state-of-the-art bank buildings. Among them was even the one who built Habib Bank — the same one we used to see on TV as kids. That firm applied too. So, eight.
00:53:15
Out of all the firms, the competition now will be among them. 21 out of 29 submitted their documents. Out of those 29, eight were shortlisted. The competition will be among those eight, and it will be a restricted competition. Bidding is something else. If I talk about everything I've told so far, you'll learn about 20% of procurement today. Remember, remember, remember—pre-qualification is always about the firm, not the product you're going to purchase. In pre-qualification, the firm's parameters are checked. It's not about whether you bring a table or a chair.
00:53:54
Come on, we’ll only get started with you once you actually show the construction or the real thing. First, why don’t you go ahead and get pre-shortlisted? Like, for your civil judge exams, there’s always a preliminary test, right? Show me that you can at least get shortlisted, then we’ll talk about the exam. Out of 29 who submitted documents, 21 made the cut for pre-qualification. The remaining 8 are still in the running. Now, among these 8, the competition starts. So tell us, how exactly do you plan to build this? This is the one, a seven-story building. Down below…
00:54:27
What exactly do you need to do? The iron system is down there, and the entire cash room is in the basement. What’s the security mechanism for all this? How will you set up cameras? What’s the security system going to be? And what about the electricity system? What if there’s a fire tomorrow and all those crores and billions of rupees stored down in the basement burn? Every single thing has to be looked at carefully. Then you talk to those eight people about it. Sir, yes, this has definitely happened before. Doesn’t the federal paper’s pre-qualification rules mention this? Actually, I read just the day before yesterday that if in pre-qualification...
00:55:02
If you get even one fear or hesitation in the qualification, just re-advertise. If needed, re-advertise a second time, and so on. Don’t stop, otherwise by the third time we’ll have to sit down with them ourselves and do due diligence to figure out what’s going on—I know it can get repetitive. Though honestly, this trend should change by now. You know why the same hurdle keeps popping up? It’s because you probably never properly looked at the evaluation criteria. When advertising, try to loosen the criteria a bit. No, sir, I’ve stuck firmly to my service CA, so who are those CAWs to argue with?
00:55:57
Maybe? He came to me right there when the project wasn’t his. You did the whole thing, but don’t talk about the person responsible, and definitely don’t mention it on camera. Alright, moving on. The third method, sir mentioned it, and madam did too — direct sourcing or the alternate method. You also asked me about it, but we’ll discuss it in detail in about an hour or so, God willing. In the open competitive process, you invite the whole world, all of Pakistan if it’s a national competition, and if it’s international, then invite everyone worldwide.
00:56:43
Here you go:
If you want to do pre-qualification, then stick with the same shortlisted people. If you're going down that route, there's no need for tendering, newspapers, ads, CAPRA, or e-pad or anything like that. Just direct sourcing. For amounts between ₹1 lakh to ₹5 lakh, you pick anyone you want directly from the three options. You get the furniture made from Pak or Germany, and then you can pay in the eighth year or later. There are other examples too, right? They'll just sell directly. Like this morning, I told you about Nespark—direct crossing to show this building to the government.
00:57:18
Okay, so we have government-to-government, then what exactly are single-stage single-envelope and single-stage two-envelope? I've already explained these methods to you. Some of you explained half, madam explained some, sir explained some. What exactly is single-stage single-envelope, single-stage? Yes, what are these? These are methods, mechanisms, nothing else. No random assumptions, procedures, you’re right, sir. Exactly, single-stage one-envelope, single-stage two-envelope, single to stage single envelope, and two-stage two-envelope — these are the four types, right? There’s nothing else beyond these.
00:58:17
Alright, now listen. There's this new thing called single stage three envelope, but you don’t really need to worry about it. Just letting you know. The only procedures that actually exist in CAPRA—and in all of Pakistan—are two stage two envelope. I always like explaining how to write these in short form to my audience. Think of it like this: single stage single envelope is 1D1, single stage two envelope is 1D2, two stage single envelope is 2'1, and two stage two envelope is 2 11, 12, 21, 22. That way, it’s way easier to remember that there are only four.
00:58:56
These are the procedures, and this is what we have. Besides this, no fifth one will come for now. That’s clear. Now, listen to the next point. All four of these are KP PEPRA lights for goods. Remember, they’re for goods. But if we exclude the third one, the first two and one are used for civil works. So if you take out the 21st, the remaining three are for civil works. Otherwise, these four all are procedures for goods. Anything else next time? The next thing is, if I say this, it wouldn’t be wrong at all.
00:59:43
So this "A" thing has been alive since the time of Prophet Adam (peace be upon him) till now. Open the lowest bid twice. Open the lowest bid twice. It's been going on since the beginning. This is the mother of all procedures. Whether you’re doing procurement yourself or getting someone to do it, if you understand this procedure properly, I challenge you — procurement will make sense to you. You won’t be confused about what to do next because I’m going to explain it in great detail, God willing. If you understand the single-stage two-envelope system and supervise a "being A" session properly just once, you’ll get it straight away.
01:00:24
Once a committee member does it themselves, I challenge you to forget procurement after that—everything else is just gossip. It's all just gossip. This is the exact procedure I'm confidently explaining to you because this is the procedure I’ve learned. Got it? Now, if you don't mind, give me a three or four-minute break. Alright, I'll quickly head to the restroom. You guys keep chatting. Please, with due respect, this registration on LMS is very important. Some of our colleagues have already done it. Yes sir, as soon as the staff finishes, that's it.
01:01:30
The session will only pause for about five to seven minutes because, first, the final assessment can’t happen without you being registered. Second, the feedback you give is tied to that. Third, the videos of the lectures you’ve attended will also be there. Yes, sir, everything will be shared with you in the group on the LMS too. We’ll take care of whatever needs to be done. This presentation will be shared in your group, on WhatsApp, and the lectures will be available on the LMS as well. Also, if this part gets clear, it’ll be even better.
01:02:24
It’s better if we handle the works and goods separately for now. We have a separate module just for works, which isn’t included here. Keep that in mind. The detailed module, like the procurement one, isn’t included here because when we do it, we prepare the works PC1 right from the start to the end. You sit down and create PC1 yourself, then move on to PC2 and PC3, managing the whole process like that. Practically, you execute it all the way through.
01:03:04
But since the course gets pretty long, they keep it separate. You’ll definitely get the details on how to do waxing, but the practical demonstrations are part of another module where we become experts. We don’t do that in between. You folks are a bit busy, so we don’t want to overload you with too much just to learn from the participants. Okay, so the next three or four slides—I’m actually going through them for the very first time here because I changed some slides last night. Now you know.
01:05:52
Electronic procurement is now in place. So, I want to explain a bit about that process to you all. But to get you thinking differently, I’ve also included the old way in the slides so you can build on what you already know. As you know, a single-stage, single-envelope process means only one envelope is submitted at a time. That envelope contains both the technical and the financial information—so both aspects are included together.
01:06:24
They’re all gathered together in the same envelope. Whatever the required time is—like, say today is October 1st and the opening is on October 18th—at the set time on October 18th, whether it’s 11:00 or 12:00, both the technical and financial bids are opened together. This is just the usual routine stuff. Things like stationery, pens, notebooks, pencils, and so on, it’s all the same. But now this whole process has shifted to electronic procurement. So how does it work now? It goes like this. First, there’s the preparation of the bidder.
01:06:55
Bidar creates his own technical bid. He downloads the bid solicitation documents that you’ve uploaded on the ePad. After downloading, he prepares his own specifications. Dell, HP, Lenovo, Sharp—each of them makes their own, and during the preparation stage, they prepare it and upload it online. Got it? He’s the one who uploads it, and the thing about that upload is no one else can decrypt it again or download it before August 18 or October 18. Once it’s uploaded, that’s it. Yeah, if you want to send an amended version...
01:07:39
Only BUD can do this if they want and are finishing it. Other committee members can't just go and download it from the iPad. The fixed time before the prescribed deadline is 11:00 AM on October 18th. Okay, sir. The encrypted file gets uploaded there, and the bidder does all of that. Now, it’s 11:00 AM on October 18th, and that’s the deadline. The system locks automatically. Late BUDs can’t come in. After 11:00 AM on October 18th, when your fixed time ends, no uploads are allowed. So, what happens then? And after that time, we...
01:08:15
Let's open the online bids. You must have seen this if you've done it before. This is a single-stage, single-envelope process where both the technical and financial parts get downloaded together at once. Both get downloaded simultaneously. Why? Because when you were setting up the e-tender, your superintendent or your IT guy had set it as a single-stage single-envelope. One court made a big mistake there. Anyway, they weren’t present themselves. I’d be upset with them because they brought in some consultant from somewhere else who set it up as single-stage true.
01:08:48
Instead of clicking on the envelope, I clicked on pre-qualification. Now that process couldn’t be completed later. Your department guy wasn’t available. They called someone else who knows IT, and the mess he made was huge—I’m talking about March, April, and May. So, you need to be careful when uploading the bid and the bidding documents. The bid solicitation document was encrypted at 11:00 AM on October 18. After that, nothing happened. At 11:30, we opened the technical and financial parts, and the same committee does the evaluation.
01:09:22
After evaluation, they give approval and award the contract. Now, about the opening time—when the opening happens, an OTP code is sent to the mobiles or emails of the three, five, or seven members involved. As soon as you enter that OTP code on the same screen, the system automatically recognizes which member it belongs to, just like how emails usually work. Hope I explained it well, sir. You’ll see all this in practice the day after tomorrow. No need to worry, I’m just giving you a heads-up.
01:09:53
Yeah, so the uploading happens online. Downloading happens online too. When the download is taking place, the procurement secretary or the goalkeeper can’t open it themselves until the respective member gets the OTP code. This is a tool to ensure transparency. Got it? You’ll see it the day after tomorrow, InshaAllah. Then the procuring agency, the entity, does the evaluation after downloading. You understand now? How it works? Sir, you can read it if you don’t mind, please turn on the speaker.
01:10:27
Sure. You'll read about the standard procedure that's been going on since the time of Adam and still continues. There's no clear routine, no complex process, and no clear definition anywhere for simple or complex. Honestly, I searched a lot to understand what simple means in procurement regimes, what complex means, and what routine means. For me, getting an ultrasound is straightforward. For you, it might be a headache. Is it a headache or not? Maybe, for me, using a scanner is impossible, but you keep getting scanning done all the time.
01:11:21
We keep watching. You know which one’s worth it, which one’s better, and which isn’t. Every day, those things are right in front of you. So, it’s a routine and simple. The simplicity depends on you. Clear, sir? Yes, sir. Third point. In this one dash one, we decide based on decision cost. But the condition is to pick the lowest responsive evaluated, not the lowest submitted unit. Clear? Yes, sir. All these submissions are done through the ePad—financial proposals, technical stuff, and financials are all uploaded there.
01:12:14
It happened. At the same time, it was downloaded on October 18 at 11:30. The committee evaluated it. That's all there is to it. Now, let's get to us. Oh yes, this is a single quotation. This was the one downloaded. It's a single-stage, single-envelope, right? Now, tell me, what other documents should be with it? There are some mandatory documents that we ask for along with the bid, right? Which ones are those? You're not getting bored, are you? Not bored? Yeah. So, which documents are those? Very good. CDR is one thing that comes physically. The rest are uploaded online.
01:12:52
Yeah. Another thing is the blacklisting mechanism. No, taxpayers have now moved everything to e-pad, right? And the e-pad itself can’t tell whether someone is a taxpayer or not. Without that, no one can file taxes. Yeah, it’s the department’s job to keep an active taxpayer list and check if someone is active or not. You need a quotation, a blacklisting document affidavit, and a CDR—ma’am said these three are the bare minimum. Other than that, whatever they’re providing should definitely include the specs in the quotation. BTW, “bit” means including taxes. Keep all this in mind. That’s about it.
01:13:34
Here's the deal. In acquisitions, when we say "bud," it means including taxes. But in actions, "bud" means excluding taxes. Got the difference? In the actions we take, the bud price never includes taxes. But whenever we talk about bud, it always includes taxes. Bud means including taxes. These contractors, especially the general order suppliers, are really tricky people. They're sneaky. What do they do? They simply write that they'll pay ₹14, and you end up winning. When you...
01:14:12
Let's call him over and say, "Sir, this is fine. I mean, I've basically won, but you should add the tax." That's why in a bit situation document, there should always be a sentence saying that whatever bit you give should include all applicable taxes. If it's not mentioned, it will be assumed that taxes are included in the bid. This sentence is really important. Got it? Moving on. Now, taxes are involved in it too. And as you just mentioned, there's also required inflation. What is required inflation? That it includes taxes and...
01:14:48
It's duty. Its validity is 90 days. It's on DDP, meaning I'll go to that area and install it for you. And it comes with a one-year warranty, and payment is exactly as you say, per your terms. Clear? These are four or five required items. This is the brand name. That's the price quotation, and Mr. Ali has that price. Now, my next question is: If you're looking at this process as a chairman, or as a member, or as the head of the department, how many types of taxes are there? On goods. On goods. Very good.
01:15:29
An Income Tax officer said one thing, a Sales Tax officer said another, and a third one talked about Service Tax. There's no Service Tax on goods, okay? I'll explain later why not. I'm asking you. Two of them have already told you. There's more. Very good. Stamp duty is 1%. Sales tax is 18%. I was saying the Income Tax was 5.5% until the day before yesterday, but just the other day, one of my participants told me it's now 8%. I said, honestly, I have no idea. So, I'm just going to leave this confusing matter here for now. Whether it's eight or five, I still think it's five.
01:16:05
Yeah, but Inshallah, I'll make sure to confirm this today. There's a fourth tax too, but that's a conditional tax. What kind of tax is it? It comes with a threshold. Generally, that's GST, right? But there's also a fourth one. Whenever you make a payment or issue a check, if the value of that check according to the purchase order is more than 1 million, then 0.02% is the Disabled Person Rehabilitation tax. So, does it exist or not? DPR 0.02 means for every 1 million, ₹200, and if it's 1.5 million, then accordingly for 1.9 million...
01:16:54
So, basically, there are these four types of taxes, amounting to about 0.02. As for all the other taxes, the builder handles those themselves. Whether it's tax paid at the time of equipment purchase or value-added tax, they take care of it on their end. Got it? I’ve told you about the four. Just recall from your old memory—those who’ve studied with me. This was the same slide and what was in the manual. We’re reading from single state to envelope, everyone. Next phase is the mother of all procedures: two envelopes submitted at the same time—one technical and one financial proposal.
01:17:41
The sealed bids, which had to be submitted by the deadline of October 18 at 11:00 AM, have been submitted. Only the technical part will be opened; the financial part remains the same. And only the qualified bidders will have their financial bids considered. Everyone else’s bids will be returned unopened. But now, bids won’t be returned unopened—they’re already sitting there. So, let’s see how that situation plays out in the ePad, which you’ll practically work on the day after tomorrow. What does the bidder do? They download the bids and the recitation document from home. They prepare two separate envelopes. Why? Because...
01:18:26
When the department was uploading this, they said it would be done on a single-stage two-envelope system. There, a scroll bar appears where you can choose one-on-one, one-on-one-two, or two-on-one, or two-on-two. The scroll bar lets you pick, and there’s also a pre-qualification in that. So, the story I’m telling you is that they did the pre-qualification, and we’re ideally doing one dash two. When I was uploading, as soon as we opened it, it created two types of files—a technical bid based on my requirements, and HP did HP Dell.
01:19:05
He quickly made a half PDF file and at the same time prepared another financial envelope. Think of it like this—he was preparing an envelope, specifically the financial one. The financial rate was quoted at half because this is my technical bid. You all already know what the technical bid is, and this is the financial bid. These two were uploaded separately. First, he had to make one file due to privacy reasons, then the other, the financial one. He uploaded both online on October 18 at 11:00 AM. However, only the technical envelope was opened—just the technical envelope was opened.
01:19:47
The online financial bid was kept sealed from the start. The program knows this is a single-stage two-envelope process. I wasn't supposed to open the financial bid, but the technical one got opened instead, and then the evaluation happened. This is the evaluation stage and that’s the preparation stage. Now tell me, this is October 18th at 11:00 AM. When should I do the contract award? When exactly should it happen? How many days has the government law given you for this work? The financial bid has also been opened. Let’s pause for a bit, just for a moment. My question is at the wrong time. Sorry, my question is at the wrong time.
01:20:31
But understand it this way: the technical side is open, and the financial side is open too. How many days do you have? Ma’am, 10-15 days? 15 or 15? Maximum 15 days. What’s the maximum number of days? Maximum 15, maximum 51, maximum 90 days. The law says you have 90 days. No need to rush. The day you open the bids will be considered Day 1 of the 90 days. Like, if it’s October 18 at 11:00 AM, that’s the first day, and from that day you have the full 90 days. You have the freedom to conduct examinations, presentations, form committees and send visits, do all the work openly, and announce the evaluation results.
01:21:35
Open the financials. The contract award and bid opening date should be 90 days from now. In technical terms, we call this the bid validity period. If you look through the entire CAPRA, the word "request" appears only once, excluding the "request for proposal" part. And if you check the whole CAPRA law, it encourages departments and committees, using very soft language. This is the only place where, in harsh terms, they’re basically giving you a hard time, implying that if you have your...
01:22:14
The Surat mid-validity period requires awarding the contract within that time. If you don't do it, I can't say for sure, but basically, it means in Urdu that you're a total international failure for not managing it even in 90 days. So now go ahead, your punishment is to ask all the bidders whether they want to extend the bid validity or not. What's bid validity? It's the price. Just look at the current US-Iran situation. Maybe when this bid was being quoted, that computer was available for 400,000.
01:22:45
Yeah, and if one or two more attacks happen after that, this will go up to 600,000. So we’ll have to take that risk within 90 days. All four big guys have to put in their own risk and give me the big price. Then I’m the useless one if I can’t get it done even in 90 days. Then the law says, if you can’t handle these exceptional circumstances, then yeah, you’re clearly useless. Now go to those four and make a request. If they extend that big amount to 500,000, 400,000, 300,000, or 250,000, that’s their kindness. Otherwise, if they don’t agree, just quietly give them your CDR. Now they have the right to forfeit.
01:23:17
Even you don’t have it. Look at the language. No, sir, the evaluation is still ongoing. Wait, wait, wait—I didn’t explain properly. I opened it on October 18th at 11:00. November 18th, December 18th, January 18th. On January 17th, I have to give the contract award to one of you four. But because of the circumstances, because of any reason, I couldn’t give it to any one of you successful bidders. Since I couldn’t give it, that means I couldn’t complete the evaluation. So either the financial bids haven’t been opened yet, or even if they have, the fault is mine. I simply couldn’t award you the contract.
01:23:54
Everyone, I’d like to ask you all something. If this process doesn’t get completed because of me, please extend your bid validity period. And if you don’t, I have no control over your bid validity or your CDR. If you do extend it, fine, do so, and let the others compete during the remaining time. If it still doesn't work out, we’ll have to readvertise. Oh, and I almost forgot to mention something else—let me tell you that now. You go ahead and speak first about your question.
01:24:41
It’s not written exactly like that—that’s a different thing which you probably don’t know yet. Here, the maximum is 90 days, but that 90 days written there isn’t really 90 days. Let me explain: if you ever feel like reading custom law, it basically says that importing something has to happen within three months. So, that 90 days is just a rough idea everyone understands for supply. However, it’s not strictly written anywhere—it could be 120 days or even 150 days. But it’s clearly stated that the contract award has to happen within 90 days.
01:25:22
I've got to do it. I’m not lazy. Now go and work hard for them. You don’t do it. I’m competing among the other three. Another thing just came to my mind. There’s a supplementary big evaluation happening within 90 days. We opened the big one on October 18th, and you have a big valid question and an answer for it. You’re the judge. You’re the chairman. He’s the head of it. One session with Judge Sahib. These four are our builders. Sir, Saeed Sahib comes and says, “I’m a contractor, I’ve got my England visa, please give me your permission.”
01:26:01
Give it to me. I want to leave now. The 90 days haven’t even passed yet. The BD evaluation is still going on. They’ll come to you. My visa’s approved. Just give me the CDR. I want to leave now. Will you give me the CDR? Sir, something like this happened in front of me. I made a request once, but I can’t do it. Then I called the committee, and no one returned the CDR. The CDR wasn’t returned, and honestly, it shouldn’t be. Allah says so. But the CDR is for feet, not for the 90 days thing.
01:27:00
Here's the deal: there’s a forfeit if you don’t act within the set validity period or finalize things within that time frame—usually within 15 days. Now, if you’re a really competent officer, you can get it done. Like, you might say, “I’m leaving, my visa got approved,” or “I can’t do it because my visa for the US or UK came through.” In such cases, the law says that if another bidder comes along during that set validity period or before you make your final award decision (which you have to do within 90 days), and you’re able to finalize things in 10, 15, or 20 days, then... well, if someone else shows up during this time, then...
01:27:35
You’ll just forfeit their CDR and call it contract competition among others. This is written in the law, in Rule number 35. Sir, completing the technical part here—yes, after 11:00 AM on October 18—and during the final decision, if any bidder comes in, the CDR can be forfeited for the remaining period. It’s only before this, not after, and not financial either—otherwise, it’s until the decision, as written in Rule number 35, about avoiding contract issues and within the bad validity period, yes, after 91 days. Feel free to ask questions openly, and we’ll do this with examples too.
01:28:47
Yeah, then that’s the end of it. He won’t get the finance, no way. The CDR is back, there are four guys; some succeeded. One of them has a daughter with him, but none of it is justified. So then what’s your response? You can’t really reply because you never awarded the contract in the first place. The revaluation process is still ongoing. We haven’t even selected the final builder yet. So the consequence is this: tomorrow I open the financial bids, and they turn out to be the lowest. What will you do then? The financial bids have to be opened the next day anyway—after 90 days.
01:29:40
Deep down, if I open it and the rate drops to the lowest, then I’ll just settle it. I’ve ended up causing a loss to the government. What answer do I have for the audit? It means you were on good terms with him. You knew the rate, right? Clear? If it finishes in one or two days, then it’s finished—just done. If you try to do it the next day, where will that money go? The next question is, no, you can forfeit it the same day, or the next day, or the third day even. You forfeit it, then we’ll inform you by letter that you’re out, and we’ve forfeited it from you—go put it in the bank.
01:30:13
Just deposit it with a simple bank, right? The money’s there. Since it’s a scheduled bank, it’s involved too. They’ll take money from you, then from there, and put it into your account. Which money? Which accounts? Here comes another question. Which account is technical? That’s it, we’re back to the start. It’s on iPad. If it’s manual, then it’s there too. So it’ll be sealed. It’ll be returned back. Sealed. Yeah. Inside it, there’s also a CDR. But those days are gone now, right? Nowadays, the sealed doc is physically with you. You’ll release it manually if it’s disqualified or something like that.
01:31:16
Otherwise, you'll get disqualified if they manually do it for you, but you opened the technical proposal yourself, ma'am. Let me refresh your memory—this doesn't happen in a single-stage two-envelope system. In a single-stage system, there's no CDR at all. The reason is, if it were there, you'd immediately know that 2% of 5 lakh is ₹10,000 or ₹400—it would be obvious right away. Okay, so they quoted ₹4 lakh, and CDR is 2%, so their rate would be clear too. Whenever someone includes a CDR, it's either been erased or an affidavit is attached. If there's no affidavit, then they tell you to bring it in, but...
01:31:56
No, they can’t do that anymore. The physical copy is already with you. There’s a new law now. That’s a good thing. I’ll definitely think about this. But it’s clear that if the CDR has physically arrived and there’s no affidavit, then bro, the CDR is already here. Technically, it should be disqualified. But I’ll think it over. Got it? The system is rule-based. It wasn’t there fully in the original Act, but then it came in the Act and then in the rules. Regulators, why can’t you find this out on the technical opening day itself? I need a special rank, seriously.
01:32:44
I created a specification based on my needs and published it, then I did an evaluation. Why didn’t anyone else do it? According to my specification, success means sitting just five people down with a good specification. Why doesn’t AI do that by itself? Here’s my answer: we are using version 1.2 or 1.5, which you’ll learn about the day after tomorrow. The Federal paper released on the night of September 28, from over four and a half months ago, already does this by itself. It’s version 2.0, which automatically handles everything. I explained this advanced stuff to you for two hours.
01:33:29
I said before that maybe next time when I’m teaching you, there’ll be some advanced stuff. So, here’s the answer to that. Now it’ll do everything by itself. We’re moving towards the pros and the guys at ProZero. That might not happen exactly, but to a large extent, it’ll handle all the conditions for the things that need to connect together. I’m telling you, you should learn AI cloud—cloud is a huge deal, with an ₹88 crore procurement. By the way, I’m diabetic, but if I had jumped on those four bids, I swear to God, I’d have gone crazy. I gave it all to the cloud.
01:34:07
He put in bids, did the examination and evaluation, and I was amazed. Then I physically checked it once—the main things are amazing. AI is incredible. Cloud services, especially not just ChatGPT, but the cloud itself is amazing. It was so complicated that even if I sat down for two months, I couldn’t have done it. I finished it all in two hours and verified each item before submitting it. The financial data we opened just two days ago will clear three or four roles from the system. Gradually, these things will phase out, and the entity will become completely human again. Then...
01:34:45
During the technical member inspection, the Head of the Department just sat there and stayed put. So, what happened next? The technical evaluation was completed. Now, the financial bids of those who were technically qualified got opened. Look at this. Some are open online, others remain unopened. The others won’t open at all because the criteria we set was that you need to score at least 70 out of 100. So, those who scored less than 70 won’t have their bids opened. For those who scored 70 or above, the system will automatically open their bids after a few days. After that, you have to enter it yourself later. The technical result is final.
01:35:20
It happened. On October 18th, we did that, and on November 8th, we uploaded the technical evaluation. As soon as we uploaded it, the result showed that there are four guys, and out of those four, one got disqualified. The rest of the team qualified. The next row will say, "Now tell us when to open their financial bids?" So, when we do that on this stage before opening the uploads, we’ll open the uploads only for those who scored 70 or above. And this is your evaluation: Stage Two—first preparation, then technical, and after that final. If anyone has any grievances at this stage...
01:35:54
So, why wouldn’t the technical team be able to handle this stage? We'll do it within these days, yes. We'll address their grievances. Our technical side is a bit weak in this area. Otherwise, the federal paper and Balochistan have done a great job, right? So, what are you going to do about this? First, you’ll do the technical evaluation, then the financial one. Until then, you won’t take any action. You can’t do anything until the finance part is sorted. There’s one more thing, sir—I’ll think about it and get back to you. It slipped my mind. That’s a really good point. I’ll share it with you.
01:36:29
Right now. There's another thing here that's really good, which I think Capra shouldn't do like this. Okay, let's move on. What exactly is single stage two envelope? Saeed saab, you start from the first line. We'll turn the speaker on. Got it? Any problem? Yes, sir. Without referring to the price. I said this is the mother of all procedures. You all need to pay close attention to this, and ask as many questions as you have right now. Ask as many questions as you want. Initially, on October 18th at 11:00 AM, we'll discuss some of the criteria here. Let's talk about the evaluation criteria now.
01:37:56
We said the bidder must have a minimum of three years of registered experience. At least three years. Got it? But Miss Sadia is my relative, and I'm making an exception for her, saying 2 years and 8 months will also work. However, that would be wrong because the three-year rule applies to everyone. I had said you need to show at least three purchase orders from public sector generator work experience, and you’ll get five points for each purchase order. Saeed Sahib submitted just one, so that's 10 points, and I added some extra points from my side.
01:38:41
I’ll give it to you. Stick strictly to the evaluation criteria. Whatever the criteria are, you’ll follow them no matter what. There won’t be any deviations. And honestly, I’m telling you this straight up. There’s still a ₹5 billion case with NAP. We really shouldn’t be getting into all the details, especially not last night. The story is basically the same. After the manual, what did they do? They took documents from others who didn’t even meet the criteria and brought those in. It’s been done like that, you know? It’s hard to make sense of it, but you get the point.
01:39:19
People have gone reading, and things have gotten messed up over there so badly that not a single person will be left. The situation is shocking to me. Exactly the same thing happened manually—that’s exactly what happened. The most technical stuff we deal with, like specific specifications or system effects, isn’t fitting in the right place. I want to answer a question you should’ve asked me: tell me, how much does 1-1 start at, and how much does 1-2 start at? And 2...
01:40:09
How much does Dash One start from, and how much does 2-2 start from? You should have asked me this question. There are no restrictions anywhere in the law. The law doesn't say that a single-stage single-envelope process must start from 5 lakh, or that a single-stage two-envelope process must start from 1 crore, or that above 5 crore it has to be two-stage single-envelope. It's up to you. Regarding your question, it’s your choice. If this seems complex, a bit difficult, or if you want the technically best option, then go for 1 DO. Otherwise, if it’s routine for you...
01:40:46
So, just go to 1 dash 1. For me, taking urine bottles, test tubes, and thousands of X-rays inside the hospital is routine. I handle crores worth on a single-stage, single envelope. But I once installed an LDRI for ₹1,25,000. I didn’t really understand how to do a single-stage two-envelope. In such a big area, I installed an LDRI for ₹1.5 lakh. It’s up to you when you use 1 dash 1. The question is, which one do you recommend and which is best for which item? Alright. Let me repeat my point again and then move on.
01:41:32
I’ll give you the answer. If it’s a routine item for you, go with "dash one." If it’s complex or natural-wise, and a bit tricky, then go with "dash two." Now, when it comes to machinery items that come with a warranty, that’s dash one. For those with warranties where you also want after-sales service, that's what you need to run. Other stuff like pens, paper, when will those come? Those come under consumables, which is dash one. So dash one covers routine consumables like paper, pens, notebooks, pencils, checks—things that have warranties and after-sales service associated with them. Machinery usually comes with after-sales service even after years.
01:42:14
Best is best furniture again. Wait a minute, if you want, my furniture is usually bought on one dash one, but if you make a good committee, you can get it on one two too, because then you have to check the wood, maybe even get it tested. It’s really up to you. Usually, people buy from SIDB, right? There was this one madam, Jamshed, who was totally against SIDB, but everyone else said, nah, they’re just trying to get out of it. Though, I was sitting somewhere, they said this needs to be removed, we plan to change it a bit later.
01:42:47
Then she herself went that way. Yeah, but before that—no, no, it wasn’t because of me going to England that anyone came. So, that’s over. By the way, you asked a really deep question. I've never thought about that aspect so much—such a strong, strong question. I didn’t even have a legal session that ready. Advertising doesn’t work, no penalizing anywhere. Yeah, that’s still there, and others have done it too—you’re not the only one. Others have done it as well. Increase by 15%? What, not 15%? Try or don’t try, just 15%, 15%, they can only go up to 15% at most, absolutely. And these days, you guys are still in touch with me.
01:44:33
They're still doing it right now, even today, and tomorrow there’s another session. The judge sent a really detailed message asking what I should do. He said, "Sir, move forward, move forward." I’m asking, which account will you put it in? Please tell me everything. Yes, about the CDR forfeiture amount, which bank—sorry, not which bank, which account will it be deposited into? That was the question right from the start. It’ll be deposited into Account One, which is the government’s account. It’ll go in there. I have an audit note on this. Honestly, sir, I’ve made only two mistakes in my life.
01:45:15
I've made even bigger mistakes that I learned from. One mistake was putting the CDR into MMC Mardan’s account. Another was an auction worth about ₹28,70,000—I also put that money into my MMC account. Because of this, I got audit remarks saying I deposited it in the treasury. But this is part of Account One, right? Since these are government funds, any money taken should go back to them. So, the audit flagged me for that. After that, we took the money out and put it into their account. Sir, moving on...
01:45:43
Sure sir, you will read it sir. Jiya sir, this slide, this point—you already know all this. I’ve already explained it. You all are just reading. Sir, only those who were technically qualified would get it open. That’s old times. No, not anymore—I’ve done this and that. Earlier, we used to return it financially. He used to tear it himself and give us the CDR to release it. Now everyone signs off. That system is done now. It’s all on the iPad now. So you’ve just got the CDR, right? Just open it and—
01:46:28
Release him. Just don’t ever make a mistake. Don’t take any extra work. Those files he kept over there—Saeed Sahib had collected one for the generator. And I took two more, kept them physically in the file, just so I could give him 10 extra marks. Don’t do that at all. Absolutely not. Back in the day, this kind of thing might’ve been forgiven. But not anymore, because now the file is up there. You can’t even change one thing in it again. You know that. Once it’s gone, it’s gone for good. What will it be? Read this. What is this? What time’s the break?
01:47:14
So, my class is at 2:00. No, it finishes at 2:00. That’s awesome, man. Really great. Yeah, then I said, trust me. Just wait a second, wait a second. There was this innocent question, you know? There was a junior judge in that room, a lady. She says, “Enough now, my brain is about to explode, I can’t understand anything.” So, for her, I revised everything. She said, “You’re giving so much knowledge nonstop that I can’t absorb it all.” So, if I tell you how I’m feeling, ma’am, since 2015...
01:48:01
Continuous procurement, continuously. One day I want to talk to you about it—you know, this was last month, in August. There was a competition held all over Pakistan, actually it was in June or May, where they wanted someone in Pakistan who had full command over all the paperwork. So, a total of 11 people were shortlisted. I was one of them. The test for eight of us was held at Air University Islamabad, and for the other three, at Air University Karachi. After the tests, three people qualified. June 19th was the fourth or fifth of Muharram, and I was here in the morning...
01:48:42
I'm in Islamabad. I had an interview. JD was supposed to come on March 17, but mine was two days before that because the next day they told me to wait, saying they might share the result with me tomorrow. Both the interview and the result were done. On June 19, they called me again. On June 19, when I was sitting in their waiting room, there were a total of three people shortlisted. One was a lady who was the Director of Policy, another was a GM from the Mines and Minerals Department, and me. Once the attendance was taken, I noticed from the results sheet that I was at the top. A little later, the interview began and lasted about an hour.
01:49:13
After the interview, they ignored me for about 10 minutes. Then I argued for almost an hour with the MD, the CAPRA MD, the PEPRA DG Legal, and a Joint Secretary—I had a really intense interview that lasted 55 to 60, even up to 120 minutes. Afterwards, when I left, I got a call at the software exchange telling me to be mentally prepared because they were selecting me. About 10 days later, I got another call. I started getting really stressed, wondering what to do next. So, I went back to these people, along with others involved, and also met some other well-wishers.
01:49:42
So I declined again. The only reason was that they were offering me the same salary. I thought, why should I go to Islamabad just to feel humiliated? Sure, it’s good for my career, but not enough for me to do all that. If I leave everything and spend 20 years of my social life with you, then everything else will be ruined. So who’s going to come and train me there? That’s why I declined that too. So this is about what you said. In 15-20 years, I learned enough, and now after 12 years, I’m standing right in front of you. And believe me, this isn’t just about studying hard. It’s all because of this.
01:50:12
So, ma’am, practical thing is, these damn contractors, they’re like your dads. The dads, they’re the real players in the market. You learn everything from them. Let’s move on. Yes, yes. I’m going slowly, slowly. But honestly, at 2:00 PM, no one is really there. This is a big injustice, man, you should’ve told me earlier. Now, this is a very interesting slide for you all. For those who haven’t studied it, and for those who have, I don’t have any issues. From ₹1 up to ₹1 lakh, single quotation, green, mail, red, shell, whatever’s written right in front of you. From ₹1 up to ₹1 lakh, single quotation if...
01:50:52
Right now, EPAD is being a bit lenient. I've already marked everything, but if you buy stuff directly from the market within 1 lakh, it’s totally fine. EPAD is silent for now, but for amounts between 1 lakh and 5 lakhs, it’s mandatory to have three quotations, and all three quotations must be on EPAD. A total of 46 people have registered themselves. On EPAD, you can assign anyone you want—for example, people from Chitral can be given to Chitral folks. If it’s in D.I. Khan, then give it to D.I. Khan, and if it’s in Mardan, then give it to Mardan. You need to check everything—just like how it was done manually back in the day.
01:51:30
You can give your three preferred people. This is mandatory on the e-pad. Now, coming to the cap from 5 lakh to 50 lakh—if the department’s website has the capra’s website shell, that’s fine. If not, just ignore it. For e-pad shell, no advertisements in newspapers are needed up to 50 lakh. It’s clear there’s no need to go to the newspaper. I’ve written this here—Rule number 11 and Rule number 19 about goods and works and the non-concept is clear. For amounts above 50 lakh, if the capra’s website shell is available on your department’s website, that’s fine. If not, then there should be two newspapers—one English and one Urdu.
01:52:16
So, the shell is clear now, that’s the main thing. We’re talking about acquisition here. From this point to that second last row, it’s all about reverse procurement. It’s about auctions. In auctions, there’s something called the reserve price, or reserve value. I always say, and I’ve been at this since morning, it’s super easy—to teach, to study, and to do stuff. But doing reverse procurement is tough. Teaching it is easy because once you’ve lost something, it’s gone. There’s no getting it back, unless someone crazy brings it back to you.
01:52:56
So, over here, you always gotta do a big due diligence. For that, a reserve price is set. Whether you’re selling something as scrap, leasing it out, or doing any kind of disposal—which I’ll explain in detail tomorrow—if that reserve value is below 10 lakh, like let’s say you have stuff lying around that’ll become scrap in a year or two, and its value comes to around ₹65 lakh, then KEPRA says if it’s below 10 lakh, just put it on my website and you’re good to go.
01:53:29
If Competition is your website, then wow, otherwise, you don’t need a newspaper or an iPad. Tomorrow, I’ll explain everything step by step. I’ve got it all ready and will show you ways you'll really enjoy. Tomorrow’s gonna be great, you’ve given me a fresh idea, and now my brain’s ready to go in 50 minutes. I’ll tell you everything tomorrow. Got all that? Now, if it’s above 1 million, then there’s the department shell—oops, I mean capital shell—and the newspaper shell too. Reverse procurement hasn’t come to the iPad yet, but it has started with federal papers from September 28 onwards in KP.
01:54:16
Not allowed for now. Alternate methods are those ways that happen without tendering, okay? Those are also a method, right? So far, we've studied open competition. Procurement plan is your mood for studying, right? You discouraged me, then okay, if you're not in the mood, just take a five-minute break and come back. Okay, this was also a part of our procurement life cycle. The first part was this—I already mentioned that this is a format used by the US as well, and KP paper uses it too. We all follow a standardized proforma.
01:54:58
We all follow this, and procurement planning should definitely be done because it has a lot of benefits—huge benefits, actually. The legal backing comes from Rule 30 and Rule 31, and Section 22 states that each department should create its own procurement plan. All procurement plans must include equal opportunities, timelines, and efficiency in a proper format. Your requirements must be documented and approved by the procuring entity. Basically, the cyber section and procurement officer will act like gatekeepers who will approve this.
01:55:36
The format says that you have to create every procurement plan once a year and upload it before July 31. The KERA website is linked with Shell. The next important thing is that you can change this procurement plan anytime during the year — 365 days. It's not written anywhere that you have to do it quarterly, monthly, daily, weekly, or hourly. There's no such rule. So, if your budget changes or something new comes up, you’re still forced to make these entries in the PIPT. But there's silence when it comes to making changes.
01:56:14
Your consumption, your consumption. There’s one question you asked me earlier this morning. I said I’ll explain it. Properly utilizing funds so that there’s no lapse. Read this. I’m not testing you, but if you’re feeling sleepy, I want to wake you up and have you explain what this means. What does it say? And for example, I’ll give you one. But first, you explain it to me. Explain it to me. What is this talking about? I just copy-pasted this from the 2017 regulations. Explain it to me in simple language. Yes sir, there’s a program plan. What does this paragraph mean? I’m not understanding it.
01:57:24
A student is supposed to be who we are and what our goal is. We have this time, so let’s use it well. Very good. Now, tell me what you call objects with me—goods, work, or services. Objects mean things you are going to take. Let me give an example. Some of you might remember the example, and if not, I’ll repeat it. For those who find it new, don’t worry. Now tell me, did any of your kids or siblings take the matric exam this time? Did anyone take it? Kids? Girls? My daughter took it, I remember. When was that date? A bit...
01:58:22
Recall that memory. Just a little bit of memory recall. What day was it? The first paper was on March 31st, alright? Because it was my daughter’s paper, I remember it. When she went to take that paper on March 31st, did God just drop the paper down from above telling her “Yes, do this one”? What happened? First, let me just tell you. One lakh students appeared for the exam under the Peshawar board. Okay, sir. Each of those one lakh students gave 8 papers, so that’s 8 lakh papers. So there must have been 8 lakh sheets. And each sheet would have 10 papers inside. So that’s 80 lakh papers. And there would be question papers too.
01:58:58
It’s reached 9 million. Plus, kids also use extra sheets, so it’s like 1 lakh, 20 thousand, 1.5 lakh, 2 lakh sheets, 80-90 lakh sheets, maybe even up to 20 million sheets. Now tell me, when my daughter went to give the exam, was Allah just tossing the papers down from above like, “Here you go, what did you do?” What I mean is, the question paper and answer paper she got on March 31 were definitely in the superintendent’s hands two days before. March 31 means it must have been given to them on March 28, so the respective superintendents in all the school areas were told, “Go ahead.” Now this 28...
01:59:33
What happened before March 28 or February 31? There wasn’t any plan. Tell me about the activities. Forget about the duties. Explain it in the context of procurement. Yes, I can come. Absolutely. Before March 28, the procurement chairman—the chairman of the board—must have received this duty from somewhere, and he would have inspected everything carefully to make sure there were no mistakes or misprints, or issues with the paper lines. So, how many days do you think this inspection would have taken? There are just 20 million papers—18 million papers. It took two months.
02:00:13
Sure. I left on January 28 and came back on February 28, then stayed until March 28. They came straight from above. What happened was, he ended up with 18 million papers. There was a tender. So how much time is needed for the tender? The printing must have happened, right? Printing takes time along with the tendering process. Let me tell you. Printing alone would take at least 30-40 days. Let’s say 40 days. So where were we on the 28th? Counting back from January 28 means we placed the order on December 28. From December 28...
02:00:53
So what if we go back? There was some bidding. At the very least, it must’ve taken about 90 days because they probably checked the printers and their efficiency. If I go back from December 28, that takes me to November 28, October 28, September 28. So from September 28, going back 15 days means the advertisement was probably done around September 13. The ad was put out on September 13, and my daughter got the paper on March 31. That’s how it was. Now read this carefully, understand this contact. It’s clear now—special functions happen at specific times.
02:01:41
Bidders also get to know which department's tenders are coming up, so to ensure transparency, this point was raised. Now, if I look at this—whether I teach it urgently or not, just hold on a bit, I’ll cover it later. Sir, your question remains here. Khalid, why did that slide disappear on me? Not sure why. Alright, I’ll take care of it. The KEPRA case is written in Section 22. Please make a note of that. It’s really important for you, especially since it’s your specific issue. KEPRA clearly states it all in one place.
02:02:35
Section 22(2) says that if your funds are already allocated and reflected in the budget book, don’t wait for the funds to be released. Complete the entire procurement process. On the day the budget is approved, issue the work order. Usually, the money gets released as well. Yes, you make the purchases and issue the orders. The bills go through, get cleared by finance, and everything gets sorted. This kind of situation has come up several times before, and in such cases, the department has always supported it.
02:03:35
The decision was made in favor of the bidder, stating that once the order is placed and there's a CAPRA notification saying funds will be released only after the funds have arrived and you've acted accordingly, if the bidder goes to collect the supply but the funds suddenly disappear, then CAPRA always rules in favor of the bidder. Within 51 days, if you tell the bidder to approach CAPRA, you can simply give them that instruction in writing. This directs the government not to recover crores of rupees from finance; instead, the government will release the funds again. According to CAPRA's decision, CAPRA is an appellate forum, so it’s not something else.
02:04:09
No, the bidder who comes first, you write to him that my budget is gone. He will directly go to Kera, and his case will be decided within 51 days. I'll explain tomorrow how he'll do that. When he does it, the decision almost always—like 99% of the time—is in favor of the bidder. It even happened to me once that I drove away a bidder like this, and the Finance Department issued ₹1 crore. In the age of LDRI and CSSD, I said no, they don’t give it. This shouldn’t be like this. Anyway, you look at ₹1, and then it’s a back-and-forth kind of thing.
02:04:44
Like, when you place an order from here, the money is taken out right then. So, even though the money was there at that time, Capra's notification says that the fund purchase order should be released only when you actually have the funds. You can base it on that — if the money was there, everything should be done then. Captain, captain, it's all injustice, pure injustice.
Alright sir, this is the format I was talking about, something any regular person can do in the field. Serial number, goods. What kind of goods? Machinery, photocopy machines, pens, paper, notebooks, civil works, construction, this and that, repair and maintenance.
02:05:38
If you have to do an auction or take services, keep adding everything. Through which method will the estimated cost go? If you need to buy furniture, when will SIDBI Park German start direct sourcing and when will they award the contract? This usually takes about 90 days, and after that, the contract is around June 30. If you need to write any remarks, just keep it simple. And you all have to do this practically tomorrow, okay? Out of the 46,000 registered people, it’s not specified space, it’s open—open except for quotations above 3 lakh, where you handle it yourself.
02:06:23
We’ll nominate the rest openly—messages will go out to all 46,000 people letting them know you’ve done it. The three quotations will only go to these three: Khalid Sahab, Asgar Sahab, and me. No matter where they are, whether from Chitral or their own respective districts, they can be anywhere. You should prefer your own district; they’ll arrange it accordingly. This won’t be under 5 lakh, and you should try to choose any three from these who are around your district. What’s the pre-qualification? I already mentioned what the pre-qualification is.
02:07:07
It's about the firm, not the product you're going to purchase. That's what I was saying. Now, look at the capability assessment of the firm to carry out the specific contract before inviting them. Before inviting, you check their capabilities—that's what we call pre-qualification. Shortlisting is part of that process. I gave you an example from the judiciary, like the civil judges' exams. When is this done? It's optional, as I've mentioned before. It's optional but applicable. Pre-qualify.
02:07:44
Orders only in the following cases: when you need to procure goods worth over ₹1 crore. Or if you have to do large and complex goods or civil works. “Large” is defined, but “complex” is not defined. Large means ₹100 million or ₹100 crore. Complex isn’t clearly defined. In those cases, you can do pre-qualification. But CAW Irrigation has already done that for their annual work. It should be based on the capabilities that the bank has set as capable. That’s your level of competency and what you have.
02:08:25
There are also resources. If the machines are to be used in northern areas, and they don’t have that kind of machines there. Resources from the middle are relevant to perform that particular assignment which will be passed here. You have to set the passing criteria — should it be 50%, 60%, or 70%. Let's keep it silent for now. After that, those who pass will be issued the bid solicitation document. The bid solicitation document shall be issued to the qualified ones. That’s how it is, sir, that’s how it is. Okay, so what all should be there for pre-qualification? For a bidder, what should be there? These documents should be for pre-qualification.
02:09:11
What kind of qualification is this? At least name some documents. We definitely haven’t been blacklisted, that’s not true at all. So yeah, it has to be in a relevant field, like the relevant Pakistan Engineering Council category. They should also be a taxpayer. We’ll check their profile to see how many banks they’ve worked with before and what kind of achievements they have. They need to have relevant experience, past experience as well, and a list of clients showing what they’ve done before. What’s their current capability today? That’s the main thing.
02:09:59
They did an amazing job. So, this guy, the 'bitter,' collected everything and also filed the 'shokas' for the firms, right? I mean, the 'bitter' collected it and filed the 'shokas.' See, this is the law—law numbers 8 and 16—I copied and pasted everything I taught. It’s all copied and pasted. There’s one word there: "list of," okay? It should be there, because your relevant experience and past performance depend entirely on that. Whose experience and performance? Exactly on this. Anyway, that’s a different matter; we don’t touch that.
02:11:17
But these things really depend on the list. This is where we do the verification. Like, what existing capabilities do you have in terms of HR, equipment, plant, and machinery? At what level are these? Also, the financial position of the last three years—that’s the main focus here, not more than that. You can consider individual years if needed. You should also have managerial capabilities, and then any particular factors—like in the example I gave about banks. Any other factors that might be deemed relevant by PE, depending on the nature and complexity of the contract.
02:11:49
Like banks, for example, but not inconsistent with the rules. These are things you need to check. Now you have to assign numbers to them. Make 20, or 15, or 100 numbers—it’s up to you. If you can’t make them, just send it to me. I’ll make it and send it back in 10 minutes. After making these, advertise it. Sorry, proof of possessing appropriate managerial experience. Engineers relevant to that work, like civil engineers, mechanical engineers, those involved in technical stuff and feasibility studies—these are for them. We’re talking about big contracts here.
02:12:29
Yeah, obviously there’s a pre-qualification for big contracts. Then there’s post-qualification too. You all—every single one of you, all 21 guys—have cleared that. But then Saeed sahib comes in and says, "At that time, Khalid sahib had all the machinery available. But he’s taken out a huge loan on it. You’re giving him the contract, but he’s already sold off all the machines." He’s an approved contractor too, right? So the question is, even after post-qualification, when you’re awarding a big contract, you’ve got to be sure. Honestly, he’s sold off all the machinery.
02:13:03
Yeah. About 15-20 days ago, or maybe 2 months ago, or even 4 months back, the loan came through. It went into default. No particular reason. The law says, then what do you do? You have to go through a verification process to confirm that everything complies with the legal, technical, financial requirements, and conditions. You have to check all that, along with verifying existing capabilities through their documents. The whole point is to ensure that the party is capable and fully meets the contract. The first one qualified, which was great, scoring 90 marks. But after seeing this situation, we moved on to the second one, who had 85 marks. Then...
02:13:38
We went to the guy with 80, and so on, posted the qualifications for the next successful one. After that, we sit one-on-one with each of them and discuss whether to move forward. It's 2 o'clock, right? Not a joke, man. Today’s the first day, you know. Hope I’m not getting played, like “Hey, he’s gonna bail from here.” We'll say the trainer ran off. No, I said, don’t kick me out from here and then say the trainer ran off. What’s that all about? No, I’m standing here out of fear. Wasn’t I standing? Don’t get bored. Huh? You guys aren’t bored, right? I left at 2, and you all will say, “He’s already taken off.”
02:14:15
Alright. Forms of the procurement notice. I mentioned to you this morning at 9:00 that intentionally or unintentionally, several words come up in procurement advertisements. So, which ones are those? I think these are the main ones. If anyone else has seen others, please share. These are the words that come up. If there are any others besides these, you can add them. These are basically the ones I’ve seen so far. Okay? Mostly, it's just these. So, note them down. I didn’t tell you to take notes until now, but now it’s time to do so.
02:15:12
First, you need to do the practical work, and then when you see the advertisement tomorrow, you have to look at it in that context. This mistake shouldn’t happen. Because if it does, it’s a big problem. Honestly, these advertisements are such a nasty thing that you end up getting disheartened right there. Whether you’re the head of the department, a member of the procurement committee, or the chairman, you think, "What mistake did I make that the letter came from the letter department?" That’s where people get discouraged. So, this is the point—I don’t want you to get disheartened right at the start. That’s all.
02:15:40
I’m gonna tell you six or seven things, and if you note them down, I challenge you that your advertisements will never go wrong. You’ll never get a letter from the camera side—that’s my promise to you. First of all, some things are now handled by the EPFO itself, but there are still some things you need to know. What are those things? Response time. Exactly, sir. So how much is it? Very good—minimum 15 days for national, and maximum 30 days for national competitive bidding (NCB). For international competitive bidding (ICB), minimum 30 days and maximum 60 days.
02:16:44
Got it noted. Now, the minimum is 15 — if it drops to 14, the Capra folks get such a sharp pain that you’ll get a letter immediately. Even if it’s 14 instead of 15. They’ve got five or six internees firmly assigned to handle this work. I’m about to explain it to you now. If even one mistake happens, you’ll get that letter the next day. If it goes from 30 to 31, or 34, or even 50, they don’t care. As soon as the minimum hits the core quantum, you’re forced to do the core quantum—that’s the legal requirement. So, keep that in mind. What’s the problem with this? It’s all one session. Today is October 1st.
02:17:31
If you give the advertisement information to the department by October 1st, they’re so efficient that it’ll come out by the next day. So please keep at least a week’s margin for them, or even better, keep it for at least 10 days—that would really help them out. Just assume, as the head of the department and chairman of the program committee, that it’ll come out on October 10th, insha’Allah. That gives you 10 days from the publication date. So if it gets published in the newspaper on October 10th, the law says the opening and closing dates should be the same. So you should keep October 25th as the closing date.
02:18:08
You need to mention that it has to be submitted on the iPad by 11:00 AM on October 25th. But if you use the old-fashioned way, like submitting within 15 days of the notification—which was the old practice—then if you sat with DI Khan and checked, those 15 days would mean something different for you. Like if someone took a local newspaper four days later, for them those 15 days would also mean something else. But the law says the submission deadline and this should be the same. So, you should leave a margin of 9 or 10 days for that. You're sending it to the newspaper today in October.
02:18:46
Got it. So, we’re expecting it on October 10th. It doesn’t matter if it comes on the 4th or 5th, but it definitely needs to be there by the 10th. After that, you’ve got to keep another thing in mind for the next 15 days. On October 25th, by 11 AM, 12 PM, 2 PM, or 3 PM, your bit must be submitted. That will be the deadline, and the next half-hour window will open after that. You have the iPad, right? Noted that down, sir. If you have any questions about this, let me know. Should I continue? This part is out of your hands now. Back in the day, your superintendent or clerk used to hide the documents. Just...
02:19:25
I used to give it to relatives. Now that it’s all on e-pad, you’ve got to mention that the bid solicitation document is available on e-pad or on KERA’s website if you want to check. Usually, they are available anyway because it’s not something to argue about. At least tell the method or procedure so the bidder knows whether I’m doing a single-stage single-envelope or two-envelope process. We have the right to announce it in the newspaper so everyone knows in advance and can upload accordingly, but they need to be informed at this stage. Yeah, 25th October. Also, confirm the other point.
02:20:08
Ask about the second point. Insha’Allah, it’ll appear in the newspaper by the 10th, so we’ll have 10 to 15 days after that. Also, the submission date and deadline should be mentioned as 25th October, counting 15 days from then, so either 24th or 25th October works. Yes, yes, yes. Mentioning brand names is considered a no-no in CAPRA and KERA, and actually worldwide it’s frowned upon. So, don’t mention the HP name in the newspaper at all. If we need a generator, don’t mention Honda either. First of all, please don’t put these names in the newspapers. If it’s absolutely necessary, then maybe you can, but...
02:20:59
Inside the bid solicitation document, you need to add that it's "or equivalent." Got it now? Miss, do you understand what I’m saying? No? Now you do? Good. First off, don’t put it in the advertisement. If it’s absolutely necessary, then inside the bid solicitation document, just add two more words: “or equivalent.” That’s what section 234 says, it’s written there. Totally fine. The bid security scan will be done on top. It doesn't show up in single-stage two-envelope bids. We erase it. You’ll get it physically. The old way is over; if you don’t give a reason, you have to provide one. I’ll talk to you first thing in the morning.
02:21:45
I’m done. Now you tell me—what kinds of bidders are there in the market for the procurements you’ve done? When you put out an advertisement in a newspaper, what kind of people show up? Very good, very good, sir. Another one—sir, very good. It’s exactly like that, sir. Please don’t make wild guesses—I’ve been guessing all morning, can you at least say something? There are four types of bidders. In works, there’s only one kind of contractor—the one registered with the Pakistan Engineering Council, whom all of us simply call a contractor.
02:22:33
There are always four types of bidders who come to you for goods. Number one is either the manufacturer. Will they be or not? They must be making something in Lahore. They’re making bedsheets for our hospital, pillows, or paper rims. All these manufacturers have their own factories scattered around Lahore and Karachi. Even in Hyderabad's Phase One Industrial Estate, there are either manufacturers or their authorized dealers. That’s how it is, sir. The third type is importers. They’re also a kind of bidder. Direct importing isn’t an easy job either.
02:23:10
No, it’s not like that. There’s full legal backing for this. Complete documentation is available. I even went personally to the port in Karachi to see the process physically and understand how it works. So, the whole import mechanism is pretty solid. And the fourth one, as sir mentioned, is the general order supplier. Basically, all the people you think of fall into these four categories. This is totally my challenge. Whoever comes to your mind will definitely fall within these four. So, you have to specifically state whether you want the item from the manufacturer, their authorized dealer, or from a general...
02:23:47
Order it from the supplier too. Now you're buying a photocopy machine. How ridiculous is it that you're asking the general order supplier for it? The general order supplier today is Khalid Associate. You've blacklisted me. Tomorrow, I'll become Khalid Enterprises. You've blacklisted me. I'll become Khalid & Co. Getting machinery items from a general order supplier is just plain foolish. So, the authorized dealer should be a proper authorized dealer, someone who brings an official authorization certificate, like the big dealers sitting here in Peshawar on the road near Gulahaji Plaza.
02:24:23
Authorization is important because the manufacturer isn’t directly involved—they’re just a Tier One partner. A Tier One partner provides proper authorization so if anything goes wrong, I’m held responsible for it. If I buy a photocopier, why would I go to Sharp or a better brand’s authorized dealer instead of just any supplier? Now, tell me—if I’m buying an ultrasound machine or some big equipment, and I go to a general order supplier, I won’t even be able to find it tomorrow. And God help the person stuck dealing with all these Chinese machines—you won’t believe the kind of stuff I’ve seen with my own eyes.
02:24:51
Here’s the translation:
"The guy is dead lying there, and they say this machine shows he’s alive. There are machines like that, but in Japan and Philips, I’m telling you, they have amazing machines that have been working perfectly for 10 years straight. But there are others who, after 6 months, were showing a dead person’s report saying he’s alive, don’t worry. And sometimes, these reports are completely outdated—I’ve seen it with my own eyes. So this is a very important point, especially keep this in mind. That’s why you call me wasting your time and mine for no reason. Please, please, please, after the 18th amendment, every..."
02:25:30
The provinces have set up their own Revenue Authorities. After the 18th amendment, all provinces created their own Revenue Authorities—for example, Khyber Pakhtunkhwa set up the KP Revenue Authority, Punjab created the Punjab Revenue Authority. Got it clear? This isn’t just a rule for goods; it applies to everything else too. The bidder has to be registered with this authority for anything other than goods. Like, if you’re buying a photocopy machine. Earlier you said, Mr. Khalid, that there are three kinds of taxes. Right from the start, you mentioned there’s income tax and sales tax.
02:26:15
There’s tax, and then there’s service tax. Service tax doesn’t apply to goods—that’s wrong. Totally wrong. Goods fall under the federal chapter. Where do you think you get money from the NFC? It comes from the amount collected as sales tax. For example, if you buy a ₹10 bottle of shampoo, sales tax is added on top of that. The government collects all that at the federal level and then distributes each state its share accordingly. So, goods have nothing to do with sales tax. Like when you buy a photocopy machine, a camera, or a table.
02:26:49
And you’re saying sales tax registration is necessary. Bro, why? This is a federal chapter. So what exactly is left that requires registration with KPRA? Both types of services—consulting and non-consulting—and third, your civil works, which are also your MRS sales. Everything you’re doing is your own production type. So for that, registration with KPRA is also necessary. To sum it up, except for goods, everything else must be registered with the Khyber Pakhtunkhwa Revenue Authority.
02:27:27
It’s mandatory except for goods. Got it? That’s all I’ve explained to you. Because whenever I get questions on this, I feel like crying and then later wonder why I didn’t explain this point properly. Got it? Let’s move on. It’s a 5-minute job. Builder’s work. You can do it online from home. It takes 5 minutes. Just give your data online. They’ll say, “Yeah, just scan and send it.” Okay, sir. Moving on. Pre-bid meeting. Pre-bid meeting. What even is that? Sir, I just heard about a new date. The meeting ends at 2:00 PM. Nobody told me this before, you guys didn’t inform me at all.
02:28:14
I had a good conversation with sir yesterday, even late at night. So, what is this? Pre-bid is very good. A pre-bid meeting means a meeting held before the bid opening. We also call it a pre-conference meeting. COVID is really something else. The rule is that this meeting should be conducted at least five days before the bid opening date you set. But if you have to do it, all these details should be published in the newspaper. Then, you have to announce in the newspaper when it’s happening. We’re doing it on 25th October. Miss.
02:28:56
We can conduct the pre-bid meeting on the 17th, 18th, or 19th, a few days before the 20th or 25th. I need to purchase a photocopy machine. So, all the relevant authorized dealers and manufacturers should come, and I will have my pre-bid meeting with them. This is a legal requirement—Rule number 37(10). If you want to do it, once you conduct this, especially in a single-stage two-envelope process, it makes things much easier and solves a lot of problems. For example, we needed to buy an ultrasound machine. Got it? Ultrasound machine. There was a new model, and you know about ultrasound machines.
02:29:34
There's always a screen attached. A new model came out, and my engineer tried to fool me by saying the standard size is 10 inches. He wrote 12 inches because about 15-20 days ago or maybe a year or 8 months ago, Philips changed it to 12 inches. But neither Shaba made it, nor GE, nor Siemens—Philips made it. I was in touch with the Philips biomedical representative, and when they decided on 12 inches, automatically everyone else was out. The other three had a pre-bid meeting just five days ago, and they were yelling about it.
02:30:11
So I started asking why they’re not giving a direct order if they know you. I looked towards Biomedical and asked why they did that. They said, “Sir, this is a really good thing.” I said, “Okay, it’s a good thing, fine. Take 10 more, and all of those became eligible too. You also became eligible. I’ll give you more marks, give you more weight technically. Equivalent ones, I’ve almost written that you have to give me the server within 30 days, deliver it on time. You say, you bidders, please have faith in God. You know...”
02:30:43
What’s the situation? This is the US and Iran. Please make it 120 days. They all start shouting otherwise. You’re forced to do it. You’ve already done 5% bit security. Please, sir, reduce it a bit. Maybe make it 4%, or even 2%. You say advance payments don’t really concern them? Okay, that’s not related to you—I won’t get into that. Otherwise, you’ll get confused. You say something else. Be clear with them that I need to take 500 screens. I’m coming with my tender. You have to apply it to the relevant destinations. Got it?
02:31:13
From Chitral and beyond. You have to do the casting yourself. It’s mentioned too. I’m explaining it as well. Everything is clear there. You wrote that there will be 10% performance security. People say make it 5% since it can go up to 10%. You can make it 5%, or 8%, all that gets discussed that day. It gets approved, and the minutes of the meeting are issued that day and uploaded on iPAT. So if these four board members were present and the other four or five checked it later, it automatically updates, showing that it was pre-bid. I just couldn’t go.
02:31:52
So, the committee approved these decisions below and uploaded them, and they tried to make it mandatory to do it on the second day if it wasn’t done that day. Okay, sir. Now, this is also really important. This whole thing I just explained in the last slide — this is its breakdown. Whatever you see on the screen, it’s based on six words. Six words: the 5 Ws plus one H. I’ve already explained this before. The 5 Ws plus one H — who’s asking? Who’s asking? The Managing Director of KPE Safe, for this 88 crore tender I mentioned, that I handled.
02:32:34
Here it is:
This is his advertisement. Who’s asking? The managing director. What? What’s he asking for? Procurement and installation of equipment, IT equipment, and allied services? What? Yeah, that’s it, sir. When? He’s asking on July 23rd at 2:30 PM. Where? Normally it’s on iPad, but the CDR has to come here, right? Where exactly? To the home office. From whom? Only from the manufacturer or their authorized dealer, no general order suppliers. Beware, no importers. We simply can’t afford to give such a big project to random folks.
02:33:25
Alright, got it. So, who, what, when, where, how — single stage two ends, and how it got cleared? You need to do these exercises by tomorrow. Tomorrow, you’ll sit in groups, I’ll organize it. Okay, sir. Yes, miss, go ahead, ask away. Ask me. What is a single state? That’s why I told you to upload the technical part. First, only the technical part will be uploaded, and it has to be opened on the same day. The bidders will upload their mandatory documents, so those will be the relevant documents. First the technical part only, then the qualified ones will be financial. Move on. Yeah. This is about goods, right? So, for goods...
02:34:15
So, about the sales tax, right? Where is it? Income, public sales—these are all goods and nowadays, everyone has to be on the active taxpayer list. It automatically updates every Monday at 11:00. Those who are already updated stay that way, and the ones who update Monday or Tuesday after, then the next Monday it's mandatory for them to be updated.
I also mentioned in this that, sir, the pre-bid meeting with interested bidders will be held on Tuesday, July 14th at 11:00 AM in the conference room of the ESEF office, KP Shah. I told the bidders about this, and they actually came physically on the 17th.
02:34:55
There were 17 participants, we had proper minutes and attendance recorded, and we uploaded all that on the KP's ePad as well as on the KP PePra website. Sir, not many bids came in, just four because everyone from All Gulaaji showed up, and maybe we might win too, but totally only four bids came, and all were from the top guys. The only thing is the rate came out higher; we asked for a higher guarantee. I hope you get the point. Anyway, it's pretty solid stuff. If you're in the mood, I can explain it now, otherwise, I’ll go over it tomorrow morning since this is an important slide and I need to put in a bit more effort on it.
02:35:35
Sir, I think this is really important. If we skip this, then I’m all fresh and energetic too. No, this is a big deal. Otherwise, I’d have done it differently. Thanks a lot, sir. If not this, then...